Timeline
2023

Start
Receiving the first light of the telescope
2022

Construction
Primary mirror overlay
2022

Construction
Secondary mirror overlay
2022

Construction
Completing the layering system
2021

Construction
Civil construction completed
2021

Construction
Telescope installed
2020

Construction
Telescope assembled
2020

Construction
Dome installed
2018

Construction
Telescope construction begins
2017

Construction
Enclosure and site construction begins
2017

Construction
Science Operation begins at the site
2016

Construction
Road construction completed
2016

Construction
Secondary mirror ordered
2016

Design
Detail design complete
2014

Design
Primary mirror is delivered to INO
2013

Design
Detail design begins
2012

Design
Road construction begins
2012

Concept
Conceptual design approved
2009

Concept
Primary mirror ordered
2008

Concept
Site monitoring begins in Gargash and Dinava
2007

Setup
Site selection concludes with Gargash and Dinava
2006

Setup
IPM hosts INO project
2003

Initiation
Four sites selected for long term monitoring
2001

Initiation
Initiation